Hombre Muerto West (HMW) Phase 1 Construction Update – Nanofiltration Plant Delivered to Site

Highlights:

  • Nanofiltration plant successfully delivered to HMW site

  • Galan and Authium teams have commenced on-site assembly. Assembly expected to be completed over the coming weeks

  • Evaporation (sylvinite) ponds for Phase 1 operations completed

  • Overall Phase 1 construction now approximately 85% complete

  • First processed brine expected early Q2 2026. First lithium chloride concentrate targeted in H1 2026

PERTH, AU / ACCESS Newswire / February 15, 2026 / Galan Lithium Limited (ASX:GLN) (Galan or the Company) is pleased to provide an update on construction progress at its 100% owned Hombre Muerto West (HMW) Project in Catamarca Province, Argentina.

Commenting from the HMW site Galan’s Managing Director, Juan Pablo (JP) Vargas de la Vega, said:

“Our HMW site team is very excited at the arrival of the nanofiltration plant. Over the past 2 years we have accumulated a lithium brine inventory of around 9,500 tonnes (LCE) in the HMW ponds. In the short term we plan to complete the nanofiltration plant assembly and commissioning, which will allow for the first processed lithium brine to be produced from HMW.

The nanofiltration plant has been designed, tested, constructed and transported on an accelerated project schedule. I would like to recognise Authium’s and Galan’s teams who have come together in a spirit of partnership to make this possible.”

Nanofiltration Plant Delivered and Assembly Underway

The Company confirms that the nanofiltration plant for Phase 1 operations has successfully arrived at the HMW project site.

Galan’s technical team, together with specialists from Authium Limited (Authium), have commenced on-site assembly of the plant. Installation and assembly activities are expected to continue over the coming weeks, after which commissioning activities will begin.

The nanofiltration plant is a key component of Galan’s processing flowsheet and will enable the efficient treatment of brine as part of the Phase 1 production process.

Sylvinite Ponds Completed

Construction of the sylvinite ponds required for the commencement of Phase 1 operations has now been completed. These ponds have been designed to accelerate the evaporation of processed brine, which leads to quicker production of lithium chloride concentrate and product sales for Galan.

Following Galan’s successful capital raising in January 2026, construction work on the evaporation ponds will continue after the nanofiltration plant has been commissioned, to allow for the expanded production rate of 5,200 tpa LCE.

Key Upcoming Milestones

Overall construction of Phase 1 at Hombre Muerto West is now approximately 85% complete, reflecting continued strong progress across processing infrastructure, evaporation ponds and supporting site facilities. As we execute the last phase of construction activities at HMW important milestones will include:

  • the completion of nanofiltration plant assembly;

  • commissioning and testing of brine processing systems;

  • first processed brine (targeted in the first half of 2026); and

  • first lithium chloride concentrate production (targeted in the first half of 2026).

The Galan Board has authorised this release.

For further information contact:

COMPANY
Juan Pablo (“JP”) Vargas de la Vega
Managing Director
jp@galanlithium.com.au
+ 61 8 9214 2150

MEDIA
Matt Worner
Vector Advisors
mworner@vectoradvisors.au
+61 429 522 924

SOURCE: Galan Lithium Limited

View the original press release on ACCESS Newswire

Staff

Recent Posts

Equitech-Bio Expands Reagent Portfolio with New IgG Offering and Publication-Backed Product Validation from Bioz

PALO ALTO, CA / ACCESS Newswire / September 8, 2026 / Bioz, Inc., the scientific…

5 hours ago

Battery X Metals to Appoint Accomplished Technology and Consumer Brands Executive Nicholas Reichenbach to Board of Directors

VANCOUVER, BC / ACCESS Newswire / September 8, 2026 / Battery X Metals Inc. (CSE:BATX)(OTCQB:BATXF)(FSE:5YW0,…

5 hours ago

BioNxt Advances Sublingual Everolimus ODF for Organ Transplant Rejection with Initiation of Large-Animal Pharmacokinetic Study

VANCOUVER, BC / ACCESS Newswire / September 8, 2026 / BioNxt Solutions Inc. ("BioNxt" or…

5 hours ago

Apex Expands Trinity Zone with Step-out Hole Returning 197.5 m Interval of 2.12% REO at the Rift Rare Earth Project in SE Nebraska

Highlights:RIFT26-019 returns 2.12% REO (1) over 197.5 m, including:4.60% REO over 5.1 m, or3.15% REO…

5 hours ago

Gaming Realms PLC Announces Interim Results

Strong growth in core content licensing business; revenue up 12% and Adjusted EBITDA1 margins expandingUK…

5 hours ago

Guardian Metal Resources PLC Announces Admission to FTSE AIM 50 Index

LONDON, UK / ACCESS Newswire / September 8, 2026 / Guardian Metal Resources plc (NYSE.A:GMTL)(LON:GMET)(OTCQB:GMTLF),…

5 hours ago